Client: Oregon Department of Aviation
Engineer:   Precision Approach Engineering
Location:   Crescent Lake, OR
Year Completed:   2018

In 45 days our company placed 12,000 CY of embankment and 11,000 tons of aggregate base to grade and compaction requirements specified for airport construction. Because of design changes, there was approximately 25% more work added to our original scope, which was completed within the original 45 day time frame.

  • 19 acres of clearing
  • 12,000 CY of excavation and embankment
  • 11,000 TONS of aggregate base
  • 3,000 TONS of asphalt paving